Mt Dora Streetscape Update

Downtown Streetscape - Phase 2
The Streetscape project will include improvements to sidewalks, right of way, underground utility, and other related improvements in the historic downtown commercial core. The goal is to improve walkability of the downtown area by increasing pedestrian access and safety, while strengthening the physical and visual connection between the downtown core and the Lake Dora waterfront. Overall, the project will improve the walkability and accessibility of the downtown, in order to benefit the merchants, residents and visitors.



Scope of Work Donnelly Street from 4th Avenue to 5th Avenue
3rd Avenue from Dora Drawdy Way to Baker Street

Tentative Schedule:
Start construction May 2014 and end by October 1, 2014
 
 
Phase 2 improvements will include:• Replace water lines and sewer lines
• Replace stormwater lines and storm inlets, improve system capacity
• Widen roadways to accommodate more/safer parking
• Reconstruct sidewalks and ramps to be ADA compliant
• Install Paver Crosswalks
• Install new landscape and Irrigation
• Install new event power
• Install new street lights
• Install new street signs
• Install new street furniture
 
 
 
Details and Plans -click link below
 
 
Meeting Notices
 
Cost Estimates The estimate is in the process of being developed from the
 
As always, I will do my best to update you on a regular basis of the progress and any information that pertains to this project and how it will affect us and benefit us. :-)
 
Karen M. Riscinto PA, CDPE
Multi-Million Dollar Producer 2013
Million Dollar Producer 2010-2012
 
Vangie Berry Signature Realty- Realtor, Branch Office Manager
Florida Lifestyle Property Management, llc - Owner/Property Manager
(Branch Office)
108 E. 3rd Ave 
 Mount Dora, FL 32757
 
(Vangie Berry Signature Realty Main Office)
2605 # C Kurt Street
Eustis, Florida 32726
352-742-7355 Office
 
 For all your "OUT OF THE BOX" Real Estate needs!

No comments:

Post a Comment